Summit Township Construction And Authorization
Procedure For Sanity Sewer And Water Main
Construction
It
is recommended that all construction bidders
obtain a written set of Summit Township
Specifications before bidding process,
as the Engineer and Contractor will be
responsible for knowledge of same.
The
Design Engineer will be responsible for
all construction inspections. Said inspections
must meet Summit Specifications. Upon
project completion, the Engineer must
submit three (3) sets of certified As
Built Drawings to the Summit Township
Department of Public Works along with
mylars.
Materials
Used Not Meeting Summit Specifications
Must Be Replaced With Approved Materials
At The Cost Of The Contractor And/Or Engineer.
No
construction may begin prior to Summit
Township reviewing plans and the Michigan
Department of Environmental Quality issuing
a permit.
No
alteration of plans after permit issued
by the Michigan Department of Environmental
Quality without prior written authorization
from same as well as Summit Township.
Water
Main pressure testing must meet Summit
Township specifications and be witnessed
by Summit Township personnel. Pressure
testing must not take place prior to Bacti-Samples
being collected by Summit Township and
the receipt of said results.
No
service connections shall be made to main
constructions until the above steps have
been complete and accepted by Summit Township.